Line Pump or Boom Pump: How to Pick the Right One for Your Pour

When you're planning a concrete pour, the pump you book changes everything, from how long you're on site to how many people you need on the deck. Get it wrong and you're paying for downtime, extra labour, or a second visit. Here is the short version of how to choose.

Aerial view of a KTK Concrete pour on a commercial site

When you're planning a concrete pour, the pump you book changes everything, from how long you're on site to how many people you need on the deck. Get it wrong and you're paying for downtime, extra labour, or a second visit. Here is the short version of how to choose.

Line pumps push concrete through ground-level hoses. They’re best for:

  • Tight sites with restricted overhead access

  • Slabs, footings, footpaths, foundations

  • Smaller volumes where setup time matters

  • Multi-storey work where the pump feeds a static placing line up the building

Boom pumps deliver concrete through a hydraulic arm with a remote-controlled tip. They’re best for:

  • Open sites with room to set up outriggers

  • Large pours where speed matters

  • Hard-to-reach areas: over buildings, into basements, across obstacles

  • High-rise work where you need vertical reach without rigging static lines

In practice it depends on the site, not the project size. A 200m³ slab on an open site is a boom job. The same 200m³ split across a tight inner-city site with overhead power lines is probably a line pump feeding a placing boom, or two pours instead of one.

What we look at before quoting:

  1. Site access and crane positioning

  2. Overhead obstructions (power, scaffold, neighbouring buildings)

  3. Pour volume and pour rate required

  4. Where the concrete needs to land, and how high

  5. Your programme: single pour or staged

If you’re not sure which is right for your job, send us the plans and we will advise which option suits.

Planning a pour? Call 0800 PUMP ON or email admin@ktkconcrete.co.nz.

Related Ideas

Site

KTK boom pump set up street-side at The Grey Apartments

What Contractors Should Ask Before Booking a Concrete Pump

Most pumping problems start at procurement. Six questions a PM or site manager should put to any pumping subcontractor before booking.

Discover more

Pumping

Planning a High-Rise Pour: What Site Managers Need to Get Right

Planning a High-Rise Pour: What Site Managers Need to Get Right

Pouring 20-plus metres vertical isn't a bigger version of a slab pour. Pump pressure, line layout, team positioning and supply rate all change, and getting it wrong means standing around waiting for trucks or blocking a line halfway up the building. Here are the six things we work through with contractors before a high-rise pour.

Discover more

Create a free website with Framer, the website builder loved by startups, designers and agencies.